constructionplanningme-blog
All About Construction Planning
1 post
Don't wanna be here? Send us removal request.
Text
All You Need To Know About Construction Planning
Good planners devote long hours of studies during the process of conceptualization of the home construction project. They conduct research and consult several technical people on the ground to aid them in order to produce the best building plans. 
Construction Planning
Construction planning sounds dull compared to swinging a sled hammer at a wall, but it is far more important. Construction planning lets builders estimate and purchase the correct amount of tools and materials needed for the job at hand.
Construction Materials
Construction materials have evolved in great ways over the years. Instead of using asbestos when building, people now use recycled materials. Construction materials are important to our safety because they're what hold the industrial world together...more at - Howstuffworks.com
Tumblr media
The Construction Planning Management Methodology
Tender Stage:
At the tender stage, the Contractor is required to produce the following:-
1. Tender Programme – Fully logic linked and rescheduled to identify the Critical Path, any float, and earliest Completion Date. Allowances for Inclement Weather and Industrial Disputes are to be made and clearly identified.
2. Tender Specific Requirements – Information required to be submitted with the Tender includes:
2.1. Tender Programme as item 1 above 2.2. Labour Histograms 2.3. Method Statements 2.4. Cash Flow 2.5. Activity Schedule
Contract Award – Contract Programme:
The Contractor is required to provide a Project Programmer who will be assigned to the project to fulfill the objectives for the duration of the Contract. The Project Programmer’s prime responsibility will be to ensure that all of the Project Programmer, Programming and Monitoring Objectives for the contract as set out in this document are met.
Tumblr media
Prior to the award of the contract, the Contractor will be required to prepare the following for acceptance by the Architect and Project Manager:
Contract Programme:
Developed from the Tender Programme on a Gantt Chart in a format in sufficient detail to allow for accurate progress monitoring for contractual purposes. The activities on the program must be fully logic linked and scheduled to identify the Critical Path to the project.
The program is to be prepared with the following Key Drivers in perspective.
Contract Period – Construction Programme:
The Contractor is required to ensure that every member of the Site Team, including specialist contractors and suppliers, must understand and fully commit to the Contract Programme.
Project Programming must be a continuous activity, hence, the preparatory groundwork of the Contract Programme must be extended by the regular preparation of Short Term Programs for both on-site and off-site activities.
The Construction Programme:
The Contractor is required to liaise with the Design Team to ensure that the Contract Programme is to be converted into the Construction Programme for the purpose of continuous programming, coordinating, monitoring and re-programming the construction works during the construction period...visit - Wikiversity.org to read more.
Tumblr media
Functions of Construction Management:
The functions of construction Management are
Planning
Scheduling
Organizing
Staffing
Directing
Controlling
Coordinating
To read more, visit - Theconstructor.org.
Choice of Technology and Construction Method
As in the development of appropriate alternatives for facility design, choices of appropriate technology and methods for construction are often ill-structured yet critical ingredients in the success of the project. For example, a decision whether to pump or to transport concrete in buckets will directly affect the cost and duration of tasks involved in building construction. A decision between these two alternatives should consider the relative costs, reliabilities, and availability of equipment for the two transport methods. Unfortunately, the exact implications of different methods depend upon numerous considerations for which information may be sketchy during the planning phase, such as the experience and expertise of workers or the particular underground condition at a site...go to - Cmu.edu to read more.
Conclusion
Understanding any sorts of service processes is only possible by getting adhered to the same. Things are the same for management services responsible for administering affordable housing. Hence, other than going haywire and perplexed about how to complete a project in a most gainful way, settling with such assistance is a diligent deal. Visit - Section 94 to know more.
1 note · View note